City Of College Park Pedestrian Bridge over Camp Creek Parkway to connect Gateway Center Hotels, Offices, Convention Center, & Arena to Downtown & MARTA via lighted, paved sidewalk
(Continued)
Safety Mesh Extended
On East Side
3/16/2025
No Obvious Progress as of 5/3/2025
All Side Rails in Place
(Need Final Fitting Together)
Side Lights Being Mounted
Sidewalk Completed to Ramp
5/16/2025
The Bridge is Essentially Finished. We are Awaiting the Ribbon Cutting Which Should Occur in a Couple of Weeks
5/31/2025